Dublin Topographical and Aerial Survey – Case Study 2026

Case Studies

Project Case Study

Dublin Topographical and Aerial Survey - Case Study 2026

Project Details

Location: Donabate, Co. Dublin
Project Length (Km): 4km road corridor, 7km watercourses
Services Provided: Topographical Survey, Mobile Mapping, UAV Survey, Hydrographic Survey, Laser Scanning

Project Overview:

The project included a detailed topographical survey of 4km of the R132 road corridor, carried out using a combination of mobile mapping and conventional survey methods. In addition, approximately 7km of watercourses were surveyed, including cross sections, hydrographic data, and laser scanning of bridge structures in accordance with OPW FRAMs requirements.

An aerial survey covering 3,500 hectares was completed, producing a high-resolution 0.1m orthophoto in ITM format. Within this, a full 3D aerial topographical survey was delivered for 1,200 hectares surrounding Donabate Village to support detailed design.

The Donabate Transport Scheme Topographical and Aerial Survey was a large-scale, multi-disciplinary project delivered to support the planning and design of key transport infrastructure in North County Dublin. The scheme required the integration of mobile mapping, conventional survey methods, hydrographic surveying, and UAV aerial data capture across a diverse and challenging environment.

The project covered a combination of busy road networks, rural land, and sensitive coastal and estuarine areas. iO Geomatics was appointed to deliver a comprehensive, high-accuracy dataset suitable for detailed design, flood assessment, and infrastructure planning.

A key component of the project was the delivery of both corridor-level and large-area survey data, including high-resolution orthophotography and a detailed 3D topographical model. The works were completed within a tight 3.5-month programme, requiring careful coordination, efficient data capture, and robust processing workflows.

 

The Challenge:

The project presented several challenges, including working safely along a busy national road, accessing watercourses in difficult terrain, and operating UAV surveys in coastal areas exposed to wind conditions. The proximity to Dublin Airport required strict airspace coordination and permissions from Air Traffic Control. In addition, the scale of the project required careful data management and efficient processing to meet programme deadlines.

Project solution

Our Project Solutions

Our Approach

iO Geomatics implemented a multi-disciplinary survey strategy to ensure efficiency, safety, and high-quality outputs across all elements of the project.

Mobile mapping was utilised along the R132 corridor to minimise time working in live traffic conditions while capturing dense, high-quality data. This approach significantly improved safety and productivity. Conventional total station surveys and double-run levelling were used to establish accurate control and validate all datasets.

Watercourse surveys were carried out using conventional methods, including detailed cross-section capture and laser scanning of bridge structures. All data was processed and delivered in accordance with OPW Flood Risk Assessment and Management (FRAMs) specifications.

For the aerial component, UAV surveys were conducted across 3,500 hectares, producing a 0.1m resolution orthophoto. A detailed 3D topographical model was generated for 1,200 hectares, providing a rich and accurate dataset for design teams. All UAV operations were coordinated with Dublin Airport Air Traffic Control to ensure compliance with airspace restrictions.

 

Project delivery

The Final Results

Key Deliverables:

  • Detailed topographical survey of 4km of the R132 corridor 
  • 7km of watercourse surveys including cross sections and hydrographic data 
  • Bridge elevations and laser scanning outputs 
  • 0.1m resolution orthophoto (ITM) covering 3,500 hectares 
  • Full 3D aerial topographical survey for 1,200 hectares 
  • Design-ready CAD and survey datasets 

Accuracy & Quality Control:

All control was established using total station and double-run levelling to ensure a high level of accuracy. Quality assurance procedures included cross-validation between mobile mapping and conventional survey data, as well as compliance checks against OPW FRAMs standards. UAV data was processed using ground control to ensure positional accuracy across the full survey area.

Results & Impact:

The project delivered a comprehensive, high-quality dataset that supports detailed design, flood modelling, and infrastructure planning for the Donabate Transport Scheme. The integration of multiple survey techniques enabled efficient data capture across varied terrain while maintaining safety and accuracy.

Project Highlights:

  • Delivery of a large-scale, multi-method survey within 3.5 months 
  • Safe and efficient survey of a busy national road using mobile mapping 
  • High-resolution UAV survey completed within controlled airspace 
  • Extensive watercourse survey delivered to OPW FRAMs specification 
  • Successful management and processing of large-scale survey data 

See More Project Results

see more projects

UAV TOpography

Topographical and Revit Model for Danu Community Special School, West Dublin

UAV TOpography

Broadmeadow Way Topographical Survey

Testimonials

What Our Clients Say

“We have worked with IO Geomatics on several public works projects, and they delivered a professional service and good quality surveys each time. Their measured surveys of historic streetscapes were a great base for one of our conservation projects."
5-Star Review from John McLaughlin Architects Katia Papkovskaia
Katia Papkovskaia
Director - John McLaughlin Architects
“Working with IO Geomatic has consistently provided us with accurate and reliable data. Their expertise in surveying has been invaluable to our projects. We recommend the services of Colin and his team without reservation.”
5 Star Review from CSEA Marcus Clifford
Marcus Clifford
Associate Director - Clifton Scannell Emerson Associates Consulting Engineers
“Shay Cleary Architects have collaborated with IO Geomatics on several projects to date, from dense urban sites to complex and demanding hillside conditions. We have always been impressed with the level of service provided and detailed survey information delivered within tight project timelines. The team are always very direct and accommodating to deal with, and we look forward to working on more projects together in the future.”
5 Star Review from Shay Cleary Architects
Karl Tobin
Architect - Shay Cleary Architects
“IO Geomatics have consistently provided accurate topographic and measured surveys to a high standard. The IO Geomatics Team site teams are professional and personable in their interactions with clients and the public. Working with their team has been a pleasure.”
5 Star Review from architect
Graham O’Sullivan
Architect